Throughout the summer, Atlanta Gas Light will continue its pipeline replacement project—a non-Emory project that will produce one-lane closures in the Emory area including Clifton, Houston Mill and North Decatur roads.
Replacement work will occur during non-rush hours and, where possible, AGL will install the pipe outside of the roadway along the public right-of-way. Any work requiring a lane closure will follow DeKalb County traffic control guidelines with signage, cones and flaggers to assist traffic flow. AGL is coordinating with the Emory to minimize inconveniences to commuters and to avoid work during commencement activities. Cliff shuttle routes will not be impacted by this project.
For questions, contact Atlanta Gas Light at 404-584-3039 or pipelinereplacements@aglresources.com.
Current work schedule:
Area of Work | Anticipated Start | Anticipated Duration | Lane Closure (all toward Emory) | Daily Schedule |
N. Decatur Road (Scott Blvd to Clairmont Ave.) | Underway | 10-12 working weeks | Westbound lane | Mon – Fri 9:00 a.m. – 4:00 p.m |
Houston Mill Road (Gatewood Road to Logans Knoll) | Underway | 5-6 working weeks | Northbound lane | Mon – Fri 9:30 a.m. – 4:00 p.m. |
Houston Mill Road (Mason Mill Road to LaVista Road) | Week of May 21 | 10-12 working weeks | Northbound lane | Mon – Fri 9:00 a.m. – 4:00 p.m. |
N.Decatur Road (Clairmont Avenue to Haygood Drive) | Week of June 11 | 10-12 working weeks | Northbound lane | Mon – Fri 9:00 a.m. – 4:00 p.m. |